"Kingwood Diversion Ditch
HCFCD entered into a contract with Neel-Schaffer, Inc. for $437,685 for preliminary engineering on the Kingwood Diversion Ditch. Within 300 days,Neel-Schaffer must:
Evaluate existing site conditions, previous studies, other projects that could affect this one, topography, rights-of-way, utilities, and soil surveys.
Evaluate existing bridges
Conduct and H&H analysis to assess existing and proposed conditions (from 2-year to 500-year storms).
Analyze Channel Improvements including the:
Impact of TIRZ #10’s latest design to replace the Northpark Bridge
Diversion structure at the confluence of Bens Branch and the Diversion Channel
Drop structures in lieu of a concrete lined channel to minimize high velocities due to the steep grade between
Walnut Lane and Deer Ridge Estates Blvd.
Develop phased construction plans based on available funding, potential impacts and benefits.
Conduct two public engagement meetings and coordinate with community groups."
 